EMERGENCY FLOOD RESPONSE

East Burnside Before
East Burnside Before East Burnside After East Burnside During

During the 2015 Christmas holidays, following record breaking rainfall, we responded to an emergency call out in Cupar. A stone burn wall had collapsed, large volumes of water had rapidly eroded the bank to only 4 meters from a new residential development. Within hours, we had mobilised plant, equipment, materials and manpower to temporarily shore up the bank while a permanent scheme could be designed and agreed.  A couple of weeks later, we were asked to design and rebuild the permanent scheme.